Construction Updates
/It has only been a little over a year since we launched Sentrina Alaminos. Since then, we made significant progress with our project development in order to provide you the with the dream homes meant for you!
The 18-hectare master-planned Sentrina Alaminos targets to construct approximately 820 house and lot units across 3 phases, including a 2.2 hectare commercial development comprising a commercial block and a commercial strip.
Construction of Phase 1 is already in full swing, with its robust total of 344 house and lot units projected to be completed by 2025.
Land Development for the area is now 40.5% complete. 46.40% of all road networks have been paved with concrete. 8% of electrical poles have been installed and have been energized. Road pavement, and installation of electricity and water distribution lines for remaining areas are ongoing. Target completion for amenity construction and land development of Phase 1 is Q4 2024.
The construction of the subdivision entryway and signage, and the brand-new Marketing Office was completed early 2021. Construction of house model units will begin by Q3 of 2021.
As of June 2021, 32% of all units have been sold (Phase 1).